Study identifies reasons for soaring nuclear plant cost overruns in the US
November 18, 2020A new analysis by MIT researchers details many of the underlying issues that have caused cost overruns on new nuclear power plants in the U.S., which have soared ever higher over the last five decades. The new findings may help the designers of new plants build in resilience to the factors that tend to cause these overruns, thus helping to bring down the costs of such plants.
Many analysts believe nuclear power will play an essential part in reducing global emissions of greenhouse gases, and finding ways to curb these rising costs could be an important step toward encouraging the construction of new plants, the researchers say. The findings are being published in the journal Joule, in a paper by MIT professors Jessika Trancik and Jacopo Buongiorno, along with former students Philip Eash-Gates SM '19, Magdalena Klemun PhD '20, Goksin Kavlak PhD '18, and Research Scientist James McNerney.
Among the surprising findings in the study, which covered 50 years of U.S. nuclear power plant construction data, was that, contrary to expectations, building subsequent plants based on an existing design actually costs more, not less, than building the initial plant.
The authors also found that while changes in safety regulations could account for some of the excess costs, that was only one of numerous factors contributing to the overages.
"It's a known fact that costs have been rising in the U.S. and in a number of other locations, but what was not known is why and what to do about it," says Trancik, who is an associate professor of energy studies in MIT's Institute for Data, Systems and Society. The main lesson to be learned, she says, is that "we need to be rethinking our approach to engineering design."
Part of that rethinking, she says, is to pay close attention to the details of what has caused past plant construction costs to spiral out of control, and to design plants in a way that minimizes the likelihood of such factors arising. This requires new methods and theories of technological innovation and change, which the team has been advancing over the past two decades.
For example, many of the excess costs were associated with delays caused by the need to make last-minute design changes based on particular conditions at the construction site or other local circumstances, so if more components of the plant, or even the entire plant, could be built offsite under controlled factory conditions, such extra costs could be substantially cut.
Specific design changes to the containment buildings surrounding the reactor could also help to reduce costs significantly, Trancik says. For example, substituting some new kinds of concrete in the massive structures could reduce the overall amount of the material needed, and thus slash the onsite construction time as well as the material costs.
Many of the reasons behind the cost increases, Trancik says, "suggest that there's a lack of resilience, in the process of constructing these plants, to variable construction conditions." Those variations can come from safety regulations that are changing over time, but there are other reasons as well. "All of this points to the fact that there is a path forward to increasing resilience that involves understanding the mechanisms behind why costs increased in the first place."
Say overall construction costs are very sensitive to upfront design costs, for example: "If you're having to go back and redo the design because of something about a particular site or a changing safety regulation, then if you build into your design that you have all of these different possibilities based on these things that could happen," that can protect against the need for such last-minute redesign work.
"These are soft costs contributions," Trancik says, which have not tended to be prioritized in the typical design process. "They're not hardware costs, they are changes to the environment in which the construction is happening. ... If you build that in to your engineering models and your engineering design process, then you may be able to avoid the cost increases in the future."
One approach, which would involve designing nuclear plants that could be built in factories and trucked to the site, has been advocated by many nuclear engineers for years. For example, rather than today's huge nuclear plants, modular and smaller reactors could be completely self-contained and delivered to their final site with the nuclear fuel already installed. Numerous such plants could be ganged together to provide output comparable to that of larger plants, or they could be distributed more widely to reduce the need for long-distance transmission of the power. Alternatively, a larger plant could be designed to be assembled on site from an array of smaller factory-built subassemblies.
"This relationship between the hardware design and the soft costs really needs to be brought into the engineering design process," she says, "but it's not going to happen without a concerted effort, and without being informed by modeling that accounts for these potential ballooning soft costs."
Trancik says that while some of the steps to control costs involve increased use of automated processes, these need to be considered in a societal context. "Many of these involve human jobs and it is important, especially in this time, where there's such a need to create high-quality sustained jobs for people, this should also factor into the engineering design process. So it's not that you need to look only at costs." But the kind of analysis the team used, she says, can still be useful. "You can also look at the benefit of a technology in terms of jobs, and this approach to mechanistic modeling can allow you to do that."
The methodology the team used to analyze the causes of cost overruns could potentially also be applied to other large, capital-intensive construction projects, Trancik says, where similar kinds of cost overruns often occur.
"One way to think about it as you're bringing more of the entire construction process into manufacturing plants, that can be much more standardized." That kind of increased standardization is part of what has led, for example, to a 95 percent cost reduction in solar panels and in lithium-ion batteries over the last few decades, she says. "We can think of it as making these larger projects more similar to those manufacturing processes."
Buongiorno adds that "only by reducing the cost of new plants can we expect nuclear energy to play a pivotal role in the upcoming energy transformation."
-end-
The work was supported by the David and Lucille Packard Foundation and the MIT Energy Initiative.Written by David L. Chandler, MIT News Office
Massachusetts Institute of Technology
Related Nuclear Power Articles from Brightsurf:
Nuclear medicine and COVID-19: New content from The Journal of Nuclear Medicine
In one of five new COVID-19-related articles and commentaries published in the June issue of The Journal of Nuclear Medicine, Johnese Spisso discusses how the UCLA Hospital System has dealt with the pandemic.
Going nuclear on the moon and Mars
It might sound like science fiction, but scientists are preparing to build colonies on the moon and, eventually, Mars.
Study analyzes impact of switch from nuclear power to coal, suggests directions for policy
A new study used data from the United States to analyze the costs and benefits of electricity production from coal-fired versus nuclear sources.
TPU researchers discover how to improve safety of nuclear power plants
Researchers at Tomsk Polytechnic University found a method to increase fuel lifetime by 75%.
Nuclear physics -- probing a nuclear clock transition
Physicists have measured the energy associated with the decay of a metastable state of the thorium-229 nucleus.
Energy-efficient power electronics -- Gallium oxide power transistors with record values
The Ferdinand-Braun-Institut (FBH) has now achieved a breakthrough with transistors based on gallium oxide (beta-Ga2O3).
Public dread of nuclear power limits its use
Nuclear power has been a part of the American energy portfolio since the 1950s, but for a number of reasons, the general public has long felt a significant dread about it.
Solar power -- largest study to date discovers 25 percent power loss across UK
Regional 'hot spots' account for the power slump and these are more prevalent in the North of England than in the south
New concept to cool boiling surface may help prevent nuclear power plant accidents
Mechanical Engineering Assistant Professor Sangwoo Shin has demonstrated a novel concept that overcomes the tolerable heat limit or what's known as the critical heat flux (CHF).
The vanishing nuclear industry
Could nuclear power make a significant contribution to decarbonizing the US energy system over the next three or four decades?
Read More: Nuclear Power News and Nuclear Power Current Events
In one of five new COVID-19-related articles and commentaries published in the June issue of The Journal of Nuclear Medicine, Johnese Spisso discusses how the UCLA Hospital System has dealt with the pandemic.
Going nuclear on the moon and Mars
It might sound like science fiction, but scientists are preparing to build colonies on the moon and, eventually, Mars.
Study analyzes impact of switch from nuclear power to coal, suggests directions for policy
A new study used data from the United States to analyze the costs and benefits of electricity production from coal-fired versus nuclear sources.
TPU researchers discover how to improve safety of nuclear power plants
Researchers at Tomsk Polytechnic University found a method to increase fuel lifetime by 75%.
Nuclear physics -- probing a nuclear clock transition
Physicists have measured the energy associated with the decay of a metastable state of the thorium-229 nucleus.
Energy-efficient power electronics -- Gallium oxide power transistors with record values
The Ferdinand-Braun-Institut (FBH) has now achieved a breakthrough with transistors based on gallium oxide (beta-Ga2O3).
Public dread of nuclear power limits its use
Nuclear power has been a part of the American energy portfolio since the 1950s, but for a number of reasons, the general public has long felt a significant dread about it.
Solar power -- largest study to date discovers 25 percent power loss across UK
Regional 'hot spots' account for the power slump and these are more prevalent in the North of England than in the south
New concept to cool boiling surface may help prevent nuclear power plant accidents
Mechanical Engineering Assistant Professor Sangwoo Shin has demonstrated a novel concept that overcomes the tolerable heat limit or what's known as the critical heat flux (CHF).
The vanishing nuclear industry
Could nuclear power make a significant contribution to decarbonizing the US energy system over the next three or four decades?
Read More: Nuclear Power News and Nuclear Power Current Events
Brightsurf.com is a participant in the Amazon Services LLC Associates Program, an affiliate advertising program designed to provide a means for sites to earn advertising fees by advertising and linking to Amazon.com.